About the project

  • 15.6-kilometre subway line that will make it faster and easier to travel within Toronto and beyond.

  • 15 stops and more than 40 connections to other transit, including GO train, subway, LRT, streetcar and bus lines.

  • Approximately 30 minutes from one end of the line to the other.

  • 28,000 fewer cars on the road each day.

 

Visit the website: www.metrolinx.com/ontarioline

Expected start date: As early as Monday April 14, 2025
Expected completion date: November 2025
Hours of work: 7 a.m. – 7 p.m.

Screenshot (465).png

At Don Mills Road and Wynford Drive

Expected start date: As early as April 1, 2025

Expected completion date: July 2025

Hours of work: Weekdays from 7:00 a.m. – 7:00 p.m.

Screenshot (461).png

Expected start date: As early as late March 2025
Expected duration: Six (6) weeks

Screenshot (462).png

Starting as early as: January 28, 2025 to Fall 2025

Hours of work: Weekdays, 7 a.m. to 11 p.m., with some overnight and weekend work

Screenshot (463).png

The Flemingdon Park segment of the Ontario Line consists of:

• Two elevated stations (Flemingdon Park and Science Centre stations)

• Elevated guideway track running North/South along Don Mills Rd.

Screenshot (464).png